Meralco Opens Bidding for 900 MW of New Power, Starting 2031

2026-10-01 · Philippines · By TipidKuryente Editorial

What it does to your bill: Nothing changes on your bill now. Contracting baseload years ahead is how Meralco avoids the supply shortfalls that cause price spikes later.

Meralco has opened bidding for another 900 MW of baseload power. It got the go-ahead once the Department of Energy certified that the contract terms it drew up fit the rules for these auctions. “Baseload” is power that runs nearly all the time, not only at the peaks, and it’s the kind of supply that keeps a bill steady instead of exposed to swings on the spot market.

The supply comes in two parts, each on a 15-year contract:

TrancheCapacityDelivery starts
First600 MWFebruary 26, 2031
Second300 MWFebruary 26, 2032

The ERC still has to approve whichever bids win. Generators can register their interest until October 15. The pre-bid conference is on November 6, and bids close on December 9.

Years away, but it matters

Nobody’s bill changes this month or next because of this. It shows Meralco trying to have contracted power in place before its demand grows, instead of buying more on the spot market. That’s the same Wholesale Electricity Spot Market whose price swings drove much of the rate news we covered from the Visayas and Mindanao this year. The more of a utility’s baseload sits under long-term contracts, the less its generation charge jumps when supply runs short and spot prices shoot up.

These deals also take years to pay off. With deliveries starting in 2031 and 2032, this round won’t touch anyone’s rate for a long while, and it adds to Meralco’s existing contracts rather than replacing any supply running today. To see how Meralco’s rate has actually moved month to month, use our rates tracker. For how the generation charge works, our guide to understanding your Meralco bill goes through each line.