ERC Clears a Much Cheaper Battery Reserve Deal for the Visayas Grid

2026-10-20 · Philippines · By TipidKuryente Editorial

What it does to your bill: No bill changes yet, since the rate is only provisional pending November hearings, but swapping expensive spot-market reserve purchases for a far cheaper contracted battery is exactly the kind of fix that could ease the premium behind high Visayas rates.

The Energy Regulatory Commission has given provisional approval to an Ancillary Services Procurement Agreement between the National Grid Corporation of the Philippines (NGCP) and East Asia Utilities Corporation (EAUC), an AboitizPower unit that runs a plant in the Mactan Economic Zone, Lapu-Lapu City, Cebu. The order, approved October 9, lets EAUC’s 44.72-MW battery energy storage system (BESS) sell backup reserves to NGCP under a five-year contract.

What the battery will supply, and at what price

Under the deal, EAUC’s battery provides NGCP with up to 13 MW of firm Regulating Reserve and 13 MW of firm Contingency Reserve, the two kinds of backup capacity NGCP draws on to keep the grid stable when demand shifts or a plant trips. The ERC set a provisional rate of ₱5.28 per kWh for both services.

Detail
FacilityEAUC 44.72-MW battery, Mactan Economic Zone, Cebu
OwnerAboitizPower, through East Asia Utilities Corporation
Contract length5 years
Regulating Reserve suppliedUp to 13 MW
Contingency Reserve suppliedUp to 13 MW
Provisional rate (both services)₱5.28/kWh
Visayas Reserve Market average~₱21/kWh
Final evaluation hearingsNovember 3 and 10

That provisional rate is roughly a quarter of the average price NGCP has been paying on the Visayas Reserve Market, the spot-priced backup-power mechanism inside the Wholesale Electricity Spot Market (WESM).

Why this lands right after the Reserve Market suspension

This approval follows closely behind the ERC’s suspension of commercial trading on that same Reserve Market, which had added roughly ₱1.29 per kWh to 2025 Visayas rates because NGCP was buying backup power at spot prices instead of locking in contracts. The EAUC deal is the kind of long-term, fixed-price contract regulators want NGCP to rely on instead: a specific example of swapping an expensive spot purchase for a far cheaper five-year agreement.

It also responds to the battery shortfall the Department of Energy flagged in its October 13 briefing, where DOE warned that the Visayas risks “substantial” red alerts in 2027 unless NGCP finishes contracting the backup capacity it was ordered to install months ago. DOE has estimated that more battery storage in the region could cut the number of power alerts by roughly half.

What’s still pending

The ERC’s approval is provisional, not final. The commission has scheduled final evaluation hearings for November 3 and 10, and it directed NGCP to dispatch the EAUC battery at least cost and to file monthly reports on the ancillary-service costs it passes through to consumers. Until that final evaluation wraps up, the ₱5.28/kWh rate and the reserve volumes could still be adjusted.

What it means for your bill

Nothing changes on a bill you’ve already received, and nothing will until the ERC’s final evaluation in November. The relevance for Visayas households is in the direction this points: a contracted battery priced at roughly a quarter of the Reserve Market average is the kind of deal that, multiplied across the 250-plus MW of battery backup DOE has ordered for the region, could meaningfully cut the spot-market costs that have kept Visayas electricity rates well above Luzon’s. For now, that stays a provisional step rather than a rate cut. Our Visayas rate breakdown tracks what’s actually driving co-op rates in the meantime.