DOE Admits 'Planning Failure' Behind Visayas Power Shortage

2026-10-07 · Philippines · By TipidKuryente Editorial

What it does to your bill: No change to Visayas brownout schedules or bills this week, but DOE's own admission that the shortfall could last until 2028 confirms this is a multi-year supply problem, not a one-off outage, worth weighing before relying on the grid alone.

Energy Secretary Sharon Garin told lawmakers on October 3 that the Visayas grid’s recurring alerts and brownouts trace back to a planning failure at the Department of Energy itself: the region hasn’t gotten a new baseload power plant in years, even as demand kept growing.

“I guess I would say it’s the planning side,” Garin said at a joint hearing of the House committees on Energy, Visayas Development, and Legislative Franchises in Bacolod City, the same hearing where Deputy Speaker Albee Benitez pushed for emergency powers to speed up construction. ACT Teachers Rep. Antonio Tinio made the same point at the hearing, saying the projections that should have flagged the shortage years in advance simply weren’t made.

The gap, in numbers

DOE data presented at the hearing put the Visayas’ available supply at roughly 2,575 megawatts against afternoon peak demand of about 2,624 MW, a shortfall of around 49 MW. The gap widens further at night, when the region leans more on power transfers from Luzon and Mindanao. Negros can produce a daytime surplus, but most of that comes from solar, which drops off right as evening demand peaks.

Garin said the shortage could persist until 2028.

What DOE is doing about it

As a short-term bridge, DOE is looking to bring in 200 to 250 megawatts of temporary barge-mounted diesel generation, which could start coming online by December 2026 or the first quarter of 2027. Garin was blunt about the limits of that fix: “These are temporary solutions,” she said, adding that the region can’t lean on batteries or diesel generation indefinitely because of cost and reliability.

For the longer term, DOE’s pipeline for Panay alone totals 775 MW of new capacity through 2030:

New capacityTarget year
135 MW baseload2028
220 MW gas-fired mid-merit2028
270 MW baseload2029
150 MW baseload2030

DOE is also advancing the Mindoro-Panay Interconnection Project, which would link the Visayas grid to the Batangas-Mindoro transmission tie.

What it means for your bill and your brownouts

Nothing changes on this week’s bill or outage schedule. What’s new is that DOE itself, not just advocacy groups or lawmakers, is now on record saying the shortage was years in the making and won’t fully close for at least two more years. The barges, if they arrive on schedule, add supply without necessarily lowering generation costs, since diesel is expensive to run.

For households in Panay, Negros, Cebu, and Bohol weighing whether to wait out the grid buildup or invest in their own backup, our solar payback comparison by utility is built for exactly that trade-off: a shorter payback period is worth more where outages, not just rates, are the problem.

Sources