Lapu-Lapu's Brownouts Have No End Date, and the City Council Couldn't Get One
What it does to your bill: If you're on MECO in Lapu-Lapu City, plan for rotational brownouts to continue for weeks: neither NGCP nor the ERC would commit to an end date at this week's council hearing.
On September 23 the Lapu-Lapu City council called NGCP, the ERC and Mactan Electric Company (MECO) to a Question Hour to explain the rotating brownouts on Mactan. Consumers came away without an end date.
Vice Mayor Celedonio Sitoy chaired the session. He said afterwards that NGCP couldn’t say when the brownouts would stop: the Visayas still doesn’t generate enough, several plants are still out, and some of the broken ones are beyond repair. He expects the shortage to last more than two months. The ERC didn’t bring a concrete action plan either.
Why Mactan is getting it
MECO has been cutting power for two hours at a time, feeder by feeder, because there isn’t enough supply to go around. That’s the same Visayas shortage we’ve been following for months: plants down on forced outage, others running below capacity, and little power coming over from Mindanao. It’s behind this past Sunday’s alert and the return to alert on the 21st. On Mactan it now shows up as scheduled outages instead of a grid-wide warning.
If you’re on MECO
Expect the two-hour rotating cuts to continue for a while. They aren’t a one-off. The council has been pressing MECO for clearer, feeder-by-feeder schedules for exactly that reason: you can’t plan a household around “no definite end date.”
Until there’s enough contracted, working capacity to cover the island’s peak demand, the cuts will keep coming, even if the schedule shifts. That’s also why homes in Mactan and the rest of the Visayas keep showing up among the country’s fastest solar paybacks. A rooftop system is the one source of supply a household controls. And if a brownout is coming anyway, it helps to know which appliances draw the most during the hours the power is on. The appliance calculator shows that, appliance by appliance.
Sources
- https://www.manilatimes.net/2026/09/28/regions/lapu-lapu-city-power-woes-worsen/2433725
- https://businessmirror.com.ph/2026/09/28/lapu-lapu-city-officials-seek-clearer-commitments-from-dus-on-power-supply/
- https://cebudailynews.inquirer.net/763604/meco-implements-rotational-brownouts-amid-power-shortage